Bolton Water Street Detention Tank

Client   -  North West Water Authority
Main Contractor   -  Miller Civil Engineering

The project was to construct a detention tank 25m deep and 25m diameter.

We provided all labour and plant to form the base and pre-cast roof section.

Duration 40 weeks
Contract Value £200,000.00

The project was completed ahead of programme and below the Target Cost.

 