Ladybower Viaducts Remedials
Client - Severn Trent Water Main Contractor
- Norwest Holst Construction
| Principle Quantities |
Demolition 2,000m3 |
|
Formwork 12,000m2 |
|
Reinforcement 120T |
|
Concrete 2,000m3
|
The project was to demolish the arches of the viaducts and recast. Due to the
constraints all demolition was carried out using hand held breakers. The
formwork had to be designed to split into manageable sections, as the use of
cranes was not possible.
Contract Target Cost Duration 26 weeks Contract Value £900,000.00
The project was completed ahead of programme and below the Target Cost.
|